This case presents situations which arose during the commissioning of a new electric melting plant in the iron foundry of a factory which manufactured machine tools. The plant and associated building works were part of a modernisation scheme and had been purchased as a fixed price "turnkey" product.
Location:
Industry:
Size:
250 employees
Other setting(s):
1978-1980

About

Abstract

This case presents situations which arose during the commissioning of a new electric melting plant in the iron foundry of a factory which manufactured machine tools. The plant and associated building works were part of a modernisation scheme and had been purchased as a fixed price "turnkey" product.

Settings

Location:
Industry:
Size:
250 employees
Other setting(s):
1978-1980