Describes the events surrounding the construction of the BAE baggage-handling system at the Denver International Airport. It looks specifically at project management, including decisions regarding budget, scheduling, and the overall management structure. Also examines the airport's attempt to work with a great number of outside contractors, including BAE, and coordinate them into a productive whole, while under considerable political pressures. Approaches the project from the point of view of BAE's management, which struggles to fulfill its contract, work well with project management and other contractors, and deal with supply, scheduling, and engineering difficulties.
Location:
Size:
365 employees
Other setting(s):
1989-1994

About

Abstract

Describes the events surrounding the construction of the BAE baggage-handling system at the Denver International Airport. It looks specifically at project management, including decisions regarding budget, scheduling, and the overall management structure. Also examines the airport's attempt to work with a great number of outside contractors, including BAE, and coordinate them into a productive whole, while under considerable political pressures. Approaches the project from the point of view of BAE's management, which struggles to fulfill its contract, work well with project management and other contractors, and deal with supply, scheduling, and engineering difficulties.

Settings

Location:
Size:
365 employees
Other setting(s):
1989-1994